8 Property, plant and equipment

(CHF million)

 

Land

 

Engineering structures

 

Buildings

 

Projects in progress

 

Movables

 

Total

Cost

 

 

 

 

 

 

 

 

 

 

 

 

Balance as at 1 January 2019

 

118.7

 

1,698.0

 

4,377.9

 

184.8

 

272.9

 

6,652.3

Additions

 

10.3

 

 

 

210.4

 

233.9

 

0.5

 

455.1

Disposals

 

 

 

–36.8

 

–55.3

 

 

 

–14.2

 

–106.3

Transfers

 

 

 

12.1

 

75.0

 

–113.5

 

18.0

 

–8.4

Reclassification

 

 

 

0.0

 

–0.3

 

 

 

0.3

 

0.0

Foreign exchange differences

 

 

 

 

 

 

 

 

 

–0.1

 

–0.1

Balance as at 31 December 2019

 

129.0

 

1,673.3

 

4,607.7

 

305.2

 

277.4

 

6,992.6

 

 

 

 

 

 

 

 

 

 

 

 

 

Balance as at 1 January 2020

 

129.0

 

1,673.3

 

4,607.7

 

305.2

 

277.4

 

6,992.6

Additions

 

9.1

 

 

 

0.8

 

234.4

 

 

 

244.3

Disposals

 

 

 

–2.0

 

–27.7

 

–10.1

 

–13.2

 

–53.0

Transfers

 

 

 

12.8

 

100.6

 

–139.2

 

16.3

 

–9.5

Reclassification

 

 

 

 

 

21.8

 

 

 

 

 

21.8

Foreign exchange differences

 

 

 

 

 

 

 

 

 

 

 

0.0

Balance as at 31 December 2020

 

138.1

 

1,684.1

 

4,703.2

 

390.3

 

280.5

 

7,196.2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Depreciation, amortisation

 

 

 

 

 

 

 

 

 

 

 

 

Balance as at 1 January 2019

 

0.0

 

–898.4

 

–2,936.5

 

0.0

 

–191.6

 

–4,026.5

Additions

 

 

 

–59.4

 

–140.3

 

 

 

–16.1

 

–215.8

Disposals

 

 

 

36.4

 

54.2

 

 

 

13.8

 

104.4

Reclassification

 

 

 

 

 

 

 

 

 

 

 

0.0

Balance as at 31 December 2019

 

0.0

 

–921.4

 

–3,022.6

 

0.0

 

–193.9

 

–4,137.9

 

 

 

 

 

 

 

 

 

 

 

 

 

Balance as at 1 January 2020

 

0.0

 

–921.4

 

–3,022.6

 

0.0

 

–193.9

 

–4,137.9

Additions

 

 

 

–58.9

 

–147.7

 

 

 

–16.7

 

–223.3

Disposals

 

 

 

1.9

 

26.2

 

 

 

12.8

 

40.9

Reclassification

 

 

 

 

 

–21.7

 

 

 

 

 

–21.7

Balance as at 31 December 2020

 

0.0

 

–978.4

 

–3,165.8

 

0.0

 

–197.8

 

–4,342.0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Government subsidies and grants

 

 

 

 

 

 

 

 

 

 

 

 

Balance as at 1 January 2019

 

0.0

 

–10.1

 

–1.7

 

0.0

 

–0.4

 

–12.2

Additions

 

 

 

 

 

 

 

–0.2

 

 

 

–0.2

Disposals

 

 

 

0.8

 

0.2

 

 

 

0.2

 

1.2

Transfers

 

 

 

 

 

–0.2

 

0.2

 

 

 

0.0

Balance as at 31 December 2019

 

0.0

 

–9.3

 

–1.7

 

0.0

 

–0.2

 

–11.2

Additions

 

 

 

 

 

 

 

–2.2

 

 

 

–2.2

Disposals

 

 

 

0.8

 

0.2

 

 

 

0.2

 

1.2

Transfers

 

 

 

 

 

–1.9

 

1.9

 

 

 

0.0

Balance as at 31 December 2020

 

0.0

 

–8.5

 

–3.4

 

–0.3

 

0.0

 

–12.2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Net carrying amount as at 31 December 2019

 

129.0

 

742.6

 

1,583.4

 

305.2

 

83.3

 

2,843.5

Net carrying amount as at 31 December 2020

 

138.1

 

697.2

 

1,534.0

 

390.0

 

82.7

 

2,842.0

Projects in progress

In the past financial year, Flughafen Zürich AG invested CHF 234.4 million in projects in progress (2019: CHF 233.9 million). The biggest items comprise the following projects:

  • Expansion and refurbishment of the baggage sorting system (CHF 67.7 million)
  • Expansion of the landside passenger zones (CHF 22.7 million)
  • Renovation of the maintenance workshop (CHF 17.2 million)

Depreciation

Depreciation of property, plant and equipment totalling CHF –223.3 million was offset against government grants and subsidies recognised in the income statement in the amount of CHF 1.2 million.

Impairment

Due to the coronavirus pandemic and the related indicators that items of property, plant and equipment may be impaired, Flughafen Zürich AG performed an impairment test (see II. Judgements and significant estimates and assumptions in the application of accounting policies, Impairment of assets in accordance with IAS 36).